GI for Pharma Process Order

Dear Gurus,

GI for Process Order ?

  1. The Business requirement is that the RM should be staged from the warehouse to Prod Storage Area , Then from the Production Storage Area (PSA) it should be consumed for the Process Line ?
  2. My concern , how to transfer the RM materials from WM to Prod Storage Area (PSA) ? what would be the triggering point for movement to PSA ?
  3. Since process order reservations are created , when the Order is created , with this Process order reservations we cannot do goods movement 311 from Warehouse to PSA
  4. We are thinking for manual reservations , apart from this any other feasible solutions as per Best Practices , can anybody share their inputs .

Regard's

Tallha

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Sep 25, 2013 at 06:32 AM

    Dear Sonalkar,

    You can try using MF60 to perform a material staging for 311 movement(either create stock transfer

    reservation or perform a direct stock transfer).

    Check and revert back.

    Regards

    Mangalraj.S

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.