Skip to Content

SAP Benefits Infotypes Date issue......

Dear All,

I have scenario where data is populating properly while creating IT0378-Adjustment Reason Data.

Some employees are eligible for Benefits in future date. So while hiring action is performed , will change the IT0171 start date to future date.

When infotype sequence is executed , after IT0171 is saved , IT0378 will be created. But here is the problem, the start date of IT0378 will be defaulted by hire date, hence Benefits area will be displayed blank. So i have changed the start date of IT0378 to start date of IT0171.Still the screen is not refreshing with proper Benefit Area , hence no adjustment reason is being populated.

Please advice...........

Thanks & Regards

JIm

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 25, 2013 at 05:05 AM

    Hi Jimson

    I believe the issue is with configuration of dynamic action, coz i have configured the same for one of the recent projects, for me when the sequential infotype is triggered to shows the current date. Request you to revert with the configuration done in V_T588Z table, screen shot of the benefit configuration will also be beneficial

    Thanks!

    Anil

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.