How can I prevent to create batch number in 107 movement type?

Dear Authorized,

I have a situation but I don't know how I solve this problem.

Our company had an EHP Upgrade. Normally, we used 107 and 109 movement types for the import trade (Import PO).

Before the upgrade, the batch number wasn't created for 107 mov. type; it was created (still is) just for 109 mov. type.

But now, the batch number is created both of 107 and 109 mov. types. Moreover, the batch number (created for 107) is saved on the MBST table.

Here are the situations:

1. We have the 107 material documents that has not any batch number(they were created before the upgrade). When we want to do goods movement based on the purchase order number, the system gives an error like "MSTB-CWESB exceeded by 2.470 KG : 110111 1200 A001 0000192900"

2. If we do goods movement with 107 mov. type, the system gives just one batch number. Then, we do goods movement with a 109 mov. type, sometimes we need to take into the stocks with more than one batch numbers. But the current system does not allow this.

Because of the urgency of the goods movements, "MSTB-CWESB exceeded by 2.470 KG : 110111 1200 A001 0000192900" (error message no: M7022) red error was turned into the yellow warning. And the goods movements are doing without any trouble now.

But I want to learn: now, there is not any control for MSTB table; and tha data on MSTB table are getting oversized.

Is this problem for the system process? How can I provide not to create a batch number on 107 mov. type? (we argue this question but in the hard code it is must to create the batch number on 107 and 167 mov. type)

Thank you,

Beste

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Sep 24, 2013 at 11:50 AM

    It is the new design that requires a batch for 107 movement, SAP explaines it in KBA 1748026 - Batch Created with Movement Type 107

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 24, 2013 at 10:07 AM

    check in the path whether for mvmt 107 batch mgmt has been activated

    Logistics general-Batch mgmt-Creation of new batches-Define batch creation for Goods mvmt.

    Read documents before turning of Batches

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.