Planned order- time changes

raju_123
Participant
0 Kudos

Hi, we are creating a z program to craeate / chnage the date and time of the planned orders. technical team abap finding it difficulty in mainntining the time in the program. while creating the planned order, it is successfully but when we display the same in change mode, system showing the time as zero.

could you please advise is it possible to maintain the time for planned orders.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In standard SAP, we have following scheduling type for planned orders

1. Backward

2. Forward

3. Current date

But scheduling type 1. Backward with time 2. Forward with time available only for production orders and not for planned orders.

Regards,

Dharma

raju_123
Participant
0 Kudos

Hi Dharma,

Is it possible to change the time of the planned orders in std sap.

Please advise.