Hi Experts,

I am facing one issue while calculating the WIP at WBS level..

Scenario:

Project having one WBS and one WBS having one networ. For network order assigned one Material and during the period( 9 th period) and cosumed same period.

My actual cost is 100

my planned revenue is 1000

Planned cost is  500..

At month end executed KKA2 system showing WIP as 100, but while doing the CJ88 system not posting WIP instad of that system posting amount to PSG ( WBS settelement profile is PSG)

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182339
Active Contributor
0 Kudos

Hello

Check in RA if you have tick marked Transfer to Financial Accounting ( T-code OKG2)

Best regards

Hrusikesh