Different type of Dates in SAP PM?

Dear Gurus,

I saw different types of dates in SAP PM like Basic start date,Basic finish date.....

Could anybody elaborate what exactly the significance of different below mentioned dates. I searched some links but i cannot get my exact requirement.

1. Actual Start Date.

2. Actual End Date.

3. Basic start Date.

4. Basic Finish Date.

5. Scheduled Start Date.

6. Scheduled Finish Date.

Regards,

Harsha.

Add comment
10|10000 characters needed characters exceeded

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2013 at 03:56 PM

    There are some threads available in forum. Please do some search. I remember same discussion happened some time back.

    http://scn.sap.com/message/5017463

    http://scn.sap.com/thread/1582346

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2013 at 05:09 PM

    Hi Varma,

    You can also refer to help.sap.com.

    Check below link

    http://help.sap.com/saphelp_46c/helpdata/EN/4c/2275df46e611d189470000e829fbbd/frameset.htm

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 23, 2013 at 06:45 AM

    Also have a look at SAP's Order Scheduling - How Does it Work info

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 23, 2013 at 03:25 PM

    Hello

    1)Bsc start - this is the date on which u want to start your work... ( no calculation is involved)

    2)Basic fin. - this is the date on which u want to finish your work. ( Priority type can influence this date..depend on priority type. which u have selected in order header.)

    3)SchedStart - this is the start date of work as per system .. this date is totally depend on scheduling type..

    example - 1 in forward scheduling it remain fixed and sched finish date & basic finish date would be varying according to the work hours in operation.

    4)Sched.Fin. - this is the finish date determined by sytem as per the scheduling type..

    example-1 - if scheduling type is backward, then basic fin. and sched fin date would be same. and sched start would be shifted according to the work hours in operation.

    note - in the case of current scheduling both type(basic and sched.) of start & finish dates remains same... as per the work hour it may overload the workcenter capacity or it may not

    1. Call Date dosn't influence bsc and schd. dates.

    2. Basic starts dates would equal to plan date of maintenance call object ( because this is only the due date)

    3. Again Basic end dates are depent on Priority type( what we have selected in Maintenance plan) & scheduling types as i mentioned in earlier reply.

    4. scheduled start/end dates depends on total work hours in tasklist and scheduling types.

    note - If we have asssigned maintenance packages to the task list and using strategy plan...

    then Order basic start date would be govern by Initial buffer in mantenance package

    and basic end date would be govern by subsequential buffer in maintenance package.

    New basic start = Plan Date - initial buffer

    new basic finish = plan date + subsequent buffer.

    the unit of these buffer is in days.

    BR,

    Rakesh