PR for unrestricted stock for project material

kunal_ingale
Active Contributor
0 Kudos

Hi All,

new to PS ,

need to know is there any way where if i add a material to project then the requirement created will be for unrestricted use ,without account assignment ,

i.e. PR generated without accoutn assignment ,

thanks

Kunal

Message was edited by: Mohamed Rafi - Basic question, Refer SAP Help.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

When you attach components to a Network Activity select the system to create reservations only.  The you will need to run MRP.  PRs wil be created for plant stock (provided you have set the Ind/Coll indicator properly in the material  master).

If you are not running MRP it doesn't make sense to create plant stock purchase reqs.

kunal_ingale
Active Contributor
0 Kudos

Hi Ken ,

thanks for reply,

here i already tried with procurement type WE (reservation)

system generated reservation but it is not gettign converted to PR

Former Member
0 Kudos

That's correct.  A reservation does not get created into anything.  The reservation is ademand for material.  The reservation is used by the MRP run.  MRP will take all of the the reservations into account and create a PR for you.  The whole point of using plant stock is to collect all of the requirements together and buy in bulk.  To do this you wil need to execute MRP.

If you just want a PR for your project then use project stock and have the network activity create a PR directly.

Former Member
0 Kudos

Hi Kunal,

Account assignment to network will be there-- but the stock from which it will take is plant stock. You just need to keep the Individual/Collective indicator as collective in MRP4 view and attach the material to a network activity.

Regards,

Jindow Joseph.

kunal_ingale
Active Contributor
0 Kudos

Hi Jindow,

Thanks for reply... do you mean to say the PR will be generated with N as account assignment..???