on 09-12-2013 12:37 PM
Dear Experts,
Here i have activated Cycle counting for warehouse and different indicators maintained in Material master .
A - Thrice in a year and float is 5 days
B - Same as above
C - Twice in a year and float is 10 days
D - Once in a year and float is 15 days
Now here in month of September i have activated Cycle counting procedure so system is showing following data with overdue status for A ,B and C indicator
But for D indicator it is showing status scheduled and New PI date is 31.12.2013
Bin Materials (A,B and C ind) Status New PI date
XYZ ZZZ ((A,B and C ind) Overdue Current system date
ABC MMM (D ind) Scheduled 31.12.2013
Now my concern over here is i do understand the date logic calculation which is based on Factory calender.But if i execute first line in above data (materials with A,B and C ind) then system is creating a document in current date say 12.09.2013 but i can enter the count there at any date it may be 11.09.2013 or 13.09.2013 and onward......So i just want to know where the float days effect will be?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.