Can raw material/production material costs can be updated on KKBC_PKO after the Cost of Production is ran?

I would like to see this transaction show the detail of the production piece of CKM3N. I don't know if this will be possible since we close the cost collectors before the Cost of Production is ran.

Accepted Solutions (0)

Answers (1)

Answers (1)

ArturoSenosain
Advisor
Advisor
0 Kudos

Hola Fernando. Your question in not 100% clear.

When you talk about "Cost of Production is run", you are talking about the Material Ledger Close ?

If this is the case, just tell you there is no report for Orders or cost collectors (KKBC_ORD, KKBC_PKO) with the cost of the components updated at the periodic price of ckm3n.

The near report of a revaluated order is CKMLQS but SAP say this is only a hint, this tcode dont give a exact value (this is stated in Note 1004597 - CKMLQS: Valuated quantity structure (multilevel) )

I often create a Z report with  PP Order (or product cost collector) revaluated at actual cost.

Im not sure if this is your question.