how to trasnfer material from one wbs to other of same project

Hi

The client wants from wbs A assigned to project x having 10 qty of matrial ,4 matrial need to be reassigned to wbs b assigned to project x.

so wbs a will have 6 matrial and wbs b will have four material. how this will be done

John

Message was edited by: Mohamed Rafi - Next time when you need any info or solution, search the forum first.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Sep 10, 2013 at 12:40 PM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 10, 2013 at 08:19 PM

    Hi John,

    Could you try in MB1B with mvt 415Q?

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 11, 2013 at 01:56 AM

    Hi,

    You can transfer stock from One WBS to Other WBS by using T Code MB1B, Use Movement Type 415 Q (Transfer Posting Project to Project).

    Have one suggestion, please search forum before posting and you will get lots of responses in the past.

    Thanks,

    Sudhakar

    Add comment