Forward & backward scheduling (1 order)

27 Views

Hello,

Let me explain the following situation;

We have an order with lets say 10 operation.

- Operation 1 -> 5 are internal operations

- Operation 6 is an external operation

- Operation 7 -> 10 are internal operations

Operation 6 "must start on" a fix date.

The previous operations (1->5) should be scheduled backwards, the subsequent operations (7->10) should be scheduled forward as from the earliest finish date of operation 6.

Can this be managed with relationships & offset?

Regards,