Want to prevent the TECHO of maintenance order for future reference dates.

Hi Gurus,

My client has one requirement, while doing the TECHO of maintenance order, the end date that we enter as ref date in techo should not be future. In my present system if I entered the reference date in future for TECHO then system is giving me a warning message but TECHO of that order is possible for future reference date. My client wants that it should be warning message but it should be error message and reference date for TECHO must not be future date. Is this possible in the SAP PM, please guide me for the settings that are required to be done to solve the above issue.

Thanks in advance.

Regards,

Parag

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Sep 09, 2013 at 11:30 AM

    You can use user-exit IWO10004, to prevent the future Reference dates. Take help of technical person to write a code accordingly in the include ZXWO1U03 of this exit.

    OR

    Follow this SPRO path (Customizing client)

    Here in the message list against IW message no. 586 change the message type W to E .

    Generate request and transport.

    Jogeswara Rao K


    Capture1.JPG (84.2 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.