on 09-07-2013 6:01 PM
Dear Expert
My client requires . I have a standard Material X exist BOM. but customer places Y material as per his requirement but system should take the standard X material . and explode the BOM in sales order how we can map this scenerio ?
Thanks and Warm Regards
Basavaraj
Hi Basavaraj,
Did you try Material determination? Try & revert. Thanks Sukant Chakraborthy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You can create material substitution condition in VB11 for material Y and then it will be redetermine material X as per the condition you will define.
Please refer this link for more detail.
http://help.sap.com/saphelp_erp2004/helpdata/en/dd/55f71f545a11d1a7020000e829fd11/frameset.htm
I hope this will help you with your requirement.
Regards,
Bhavin Joshi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please create BOM for your material X and have Material Determination functionality between your X and Y materials, wherein the material X would be subtituted when the material Y is entered.
Please let me know for any further clarification.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Have you test this with material determination?
Thank$
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.