Dear All,

We are doing consumption (261 movement) of Natural Gas in process order.

We are mantaining info record thru me11. We are also changing rate or Natural Gas with validity perio

During month end we are receiving bill from vendor and settle thru MRKO.

In some cases it might be possible that we forgot to change latest rate in info record.

During MRKO we come to know that billing rate is diff. than rate maintained in info record. We are chaning rate with effect date.

But in MRKO it consider rate which was during consumption of material.

Due to this we are getting diff. between actual bill and document posted in SAP.

Is it possible that, during MRKO system again consider rate from info record ?

Thanks and Regards,