Hello Guru's,

I want to create PI-sheet for process order i have searched about it in sdn but not able to get step by step procedure to create PI sheets.

please tell me the complete procedure step by step to create PI sheets with T-codes.

Regards,

Dheeraj Rawal

Accepted Solutions (1)

Accepted Solutions (1)

former_member208398
Active Contributor
0 Kudos

Hi Dheeraj,

Kindly check the document shared below in SCN:

http://scn.sap.com/docs/DOC-41295

I think it will help you.

Best Regards,

Rajen

former_member211613
Active Participant
0 Kudos

Hello,

Thanx for providing me document but when i am going to create PI sheet after releasing process order system is giving me error " Inspection lot not found for process instruction of type "5" "

how to resolve it.

Regards,

Dheeraj Rawal

Former Member
0 Kudos

Hi Dheeraj,

Pls remove inspection type 05 in MMR & assign new inspection type as 03.

During process order release system will create inspection lot & system generate control recipe.

check t.code CO53 & CO54 after control recipe created.

check & revert.

Tnx

former_member211613
Active Participant
0 Kudos

hi,

In CO53 i am getting 2 control recipe but when i am clicking on send button system is showing error

"

Control recipe has not been sent to destination

"

and for  another control recipe when i am clicking on send button  system showing me pop up as " control recipe for des. type 3  can not be downloaded "

please provide me solution for both recipe.

Regards,

Dheeraj Rawal

former_member211613
Active Participant
0 Kudos

Hi,

i have successfully created PI sheet but in t-code CO60 i am getting cockpit black i want to add phase wise characteristics. what settings i have to made.

Please help.

Regards,

Dheeraj Rawal

biplob_chowdhury15
Active Participant
0 Kudos

Hi Dheeraj,

Go to master recipe select phase and operation then goto in top-select process management - process instruction-here you maintain process instruction category.

Then select process instruction -go to characteristic overview- maintain characteristics and values here.

Create process order- generate control recipe-.

Then go to CO53XT - enter plant here- click on cretaed, sent

This screen will come

click on send here.

then go to CO60XT

Click on work instruction - screen will be executed maintain PI sheet. maintain and save it.

If anything please revert back.

Thanks,

Biplob

Answers (1)

Answers (1)

diwakar_sharma3
Explorer
0 Kudos

Hi Dhreej,

  To specify the PI that is to be generated in the process order when control recipe is created for the control recipe destination.  There are steps to be performed such as

1) Define control recipe destinations
2) Assign PI Categories
3) Set process instructions to be generated automatically

Basic steps in PP-PI:
1.(a) In the master recipe, process instructions are attached to the phases.
b) While creating a process order, the control recipe will be created, which will contain the process instruction.
c) control recipe will be sent to a proper destination and control recipe will be sent back to the process order and instructions with the data will be available
2) Define profile with default values
3) Assign Material Types
4) Define Recipe Status
5) Define Recipe Usage
6) Define Priority Sequence for auto recipe selection
7) Define Order types
😎 Define Order type Dependent parameter
9) Define Number Ranges
10) Process Management
11) Transport Management characteristics
12) Transport Predefined Messages characteristics
13) Define & setup control recipe destination
14) Define process messages characteristics
15) Define & setup message destination
16) Define & setup process message characteristics
17) Define Process Instruction

These above configuration steps are compulsory maintained in the IMG activity.

Regards

Diwakar


former_member211613
Active Participant
0 Kudos

Hi,

I have created PI sheet cockpit but i want to ass fields there where i will define them

eg. I want cockpit like that

Phase 0020              Process Order : 123456

Planned Quantity :

Confirmed Quantity :

Unit of Measurement :

now where i have to define these fields like planned qty , Conf. Qty, UOM and etc.

Currently i am getting black cockpit

Regards,

Dheeraj

biplob_chowdhury15
Active Participant
0 Kudos

Hi Dheeraj,

Before creating PI cockpit you have to do some config.

You have to assgin

Phase 0020              Process Order : 123456

Planned Quantity :

Confirmed Quantity :

Unit of Measurement :

in process instruction category. T/code- O12C

Check  APHASE_1, AORD_1, PH_CON  - copy required characteristics for phase, process order, planned qty, confirm qty, unit of measurement  and make one Z- process instruction category.

Assign this Z- process instruction category to Master Recipe  -  select phase and operation then in the top go-to process management process instruction. - Assign Z-process instruction category here what you have just created.

Now create process order, before release update charactertistic value like issue item, batch etc , then release process order, generate control recipe.

Process order, phase, qty will be automatically update in PI cockpit.

Please do it carefully. If anything pl. revert back.

Thanks,

Biplob