Bottom up rescheduling of SNP planned orders

57 Views

Dear all

I have the following example:

I have a demand.

A SNP PDS with finished product A, component B and raw material C. . The leadtime to produce product A is only 2 days. However the leadtime of raw material C takes longer. Will the SNP heuristics push out the planned order for product A for 2 months, or will it not take into account the lead time of raw material C?

Is there any kind of bottom up functionality availalbe in SNP, can CTM do this? See also attached picture how the rescheduling should take place in SNP.