Skip to Content
0
Former Member
Sep 02, 2013 at 11:33 AM

Subcontracting Issues for ME2O transaction

39 Views

Hi All,

In Subcontracting when we do Transfer posting of Child components to SC vendor at ME2O, the Purchase order number is not storing the material document.

As a result of this at the time of MIGO I am not able to assign the Challan. The ssytem throughs an warning nessage as " Challan Material is differnet from the material document"

If I do the transfer posting at MB1B the PO number is getting stored in the material doc. hence also i can assign the challan at MIGO.

My client wants to use ME2O. They don't want to use MB1B..

If I use ME2O for Transfer Postings then in the material doc resulted with that transfer posting will not contain the PO number.

Hence I am not able to assign the challan created with that mat doc at the time of GR.

Can any body tell me how correct this issue.