Only use resources of the same type for the reference resources

I have a resource CIFed from R3 WC and its functioning properly .This WC is using a reference capacity (not a ref workcentre) .This Workcentre is created as a multimixed due to multiple capacities.

Now i want to change the capacity from 2 to 4 and for that tried to do RIMODINI as CFm2 is not updating the capacities to 4.

during this I am getting an error as "Only use resources of the same type for the reference resources"  Message no. /SAPAPO/DMRES119. and CIF steps failes and unsuccessful to transfer the changes.

Appreciate the pointers on this issue .

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 22, 2013 at 03:36 PM

    For this question also i got the answer on my own this workcentre has two categories of capacity.1 Machine and 2.Labour. Labour capacity has a ref capacity in which the indicator for "Can be used by several operations" was checked but not in the basic workcentre under category 002.this was creating issues with above error. aligned the settings and issue got resolved.