Prerequisites : Creation of Forecast (FRC) delivery schedule for scheduling agreement ???

Hi SAP Experts ,

I want " automatic " creation of forecast (FRC) delivery schedules or schedule lines under a scheduling agreement. What are the "prerequisites" that need to be defined under material master and vendor master for the above scenario to happen ?

Pl explain in details.

Thanks ,

Sanket Kumar

SAP MM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Aug 30, 2013 at 05:03 PM

    Dear Sanket,

    By Using MRP you can generate schedule lines automatically against a scheduling agreement, but whether it is JIT or forecast purely depends on your selection while generating schedule lines in ME84 Transaction or in ME38 transaction Menu bar>>>edit... generate JIT or forecast schedule.

    To generate schedule lines automatically follow below steps.

    1.Create scheduling agreement with doc type LPA

    2. Create source list & enter Schagrmt number in outline agreement field and mark the line relevent schedule line MRP.

    3. while running MRP ex in transaction MD03 select schedule lines creation.

    For further queries please get back to me.

    Regards

    Satish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.