Concept & Usage of Release Creation Profile in Scheduling Agreements?

0 Kudos

Hi SAP Experts ,

I would like to understand the following aspects as mentioned below in context of " release  creation profile " in the process of creation of scheduling agreement ?

1.) concept and why it is used in scheduling agreements ?

2.) how it is used in scheduling agreements in SAP ?

Prompt answer is appreciated.

Sincere regards,

Sanket Kumar

SAP MM

Accepted Solutions (0)

Answers (1)

Answers (1)

satishbabu_bodepudi
Contributor
0 Kudos

HI Sanket,

Release Creation profile is the one which actually makes the difference between JIT schedule and Forecast delivery schedule. IF you don't assign any release creation profile to the scheduling agreement then there is no difference between JIT & forecast delivery schedule. This Can be understand in print out of messages LPJ1 & LPH1 for same schedule lines. It also controls which schedules lines are to be sent in which type of release. Ex. only NEw, changed, next date etc.

Create release creation profile with below details in aggregation tab.

>>>>>>>>>>>>>JIT>>>>>>>>Forecast

No agregation 0>>>3>>>>>>>>0>>2

Daily Aggregation 4>>7>>>>>>3>>5

Weekly aggregation(blank)>>>>6>>30 (Not possible with JIT)

Monthly aggregation(blank) >>>>31>>>180 (Not possible with JIT)

Ex. In ME38 maintain schedule lines as below

date>>>>>>>Qty>>>>time

30.08.2013>>15>>>>14.30

30.08.2013>>>20>>>15.30

31.08.2013>>>20>>>>15.30

01.09.2013>>>15>>>>16.30

01.09.2013>>>>15>>>18.30

02.09.2013>>>>30>>>14.30

02.09.2013>>>>15>>>16.30

03.09.2013>>>>50>>>>18.30

04.09.2013>>>>30>>>14.30

04.09.2013>>>>15>>>16.30

06.09.2013>>>>40>>>16.30

10.09.2013>>>>30>>>16.30

15.09.2013>>>50>>>14.30

01.10.2013>>>>50

01.11.2013>>>>30 so on on first of every month till next 12 months

Generate JIT & forecast release without assigning any release creation profile.

Result: All schedule lines will be sent as maintained above.

Now assign Release creation profile & generate both JIT & forecast

Result: JIT

30.08.2013>>15>>>>14.30

30.08.2013>>>20>>>15.30

31.08.2013>>>20>>>>15.30

01.09.2013>>>15>>>>16.30

01.09.2013>>>>15>>>18.30

02.09.2013>>>>45

03.09.2013>>>>50

04.09.2013>>>>30

Result: Forecast

30.08.2013>>15>>>>14.30

30.08.2013>>>20>>>15.30

31.08.2013>>>20>>>>15.30

01.09.2013>>>30

02.09.2013>>>>45

03.09.2013>>>>50

Week X >>>115

Week Y >>>50

Week Z>>>50

month 11 >>30

month 12 >> 30

month 1    >>>30

month 2 >>30

month 3 >> 30

note: the above is approx guess may not be same depends on working days

Here system will not consider the remaining schedule lines after 7th day in JIT or 180th day  in forecast day from today as maintained in creation profile(release horizon: total work days). 

Hope it is helpful

Regards

Satish