Can lead times on SAP Business One be associated with the vendor or the item?

Hi,

We are are a packaging firm about to load the master data to SAP Business One.

Can anyone say if the lead times when loading the item master are specific to the items or the supplier?

Regards,

Martin

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 30, 2013 at 06:27 PM

    Hi Martin,

    Lead time can be set for Item only. System does not support lead time to link to supplier.

    Thanks,

    Gordon

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 30, 2013 at 10:40 PM

    Hi,

    Are you uploading item master data through DTW?

    If yes, i would suggest with items. because you can use "preferred vendor" option under purchasing tab.

    Thanks & Regards,

    Nagarajan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.