How to create outbound delivery automatically when an inbound delivery is created ?

Hi,

We have 3 business entities namely

1. Sales and Distribution Unit

2. HUB

3. Manufacturing Unit.

The Scenario is Make To Order hence, the process is as follows:

SO is created for end customer in SD Unit, which creates a PO in HUB. Hub dosen't store any material stock, so this creates a PO at manufacturing Unit. With reference to these PO's an SO is also created. Once manufacturing unit is done with the production of material, outboubd delivery is created. This delivery automatically creates an inbound delivery at HUB, which should trigger an outbound delivery from HUB and inbound delivery to SD Unit.

Problem: We are able to create automatic PO-SO chain using IDOCs. Automatic Inbound delivery at HUB is also created on creation of Manufacturing plant's Outbound delivery, but, I am stuck at creating Outbound delivery at HUB as soon as an Inbound is created. We are using IDOCs for data transfer, so let me know if this is possible using IDOCs.

Please guide me how this can be done.

Regards,

Madhav

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Aug 27, 2013 at 06:48 AM

    Hi Madhav,

    I have no out of the box solution for this but I would go for something which triggers for the specific sales order (item) the VL10 batch delivery creation process or a BAPI. That could be done by a periodic job, by an business transaction event or by a special output type processing triggered through the inbound delivery. The last would be my favourite as this approach gives good means to trace the process as every user can check if this output type has been found and processed.

    An idoc solution would be possible but this also must be triggered by an output processing from the inbound delivery. My feeling is that this effort means more workload to be setup.

    Best regards,

    Oliver

    Add a comment
    10|10000 characters needed characters exceeded

    • Madhav,

      Can you check your partner determination setting. How this perticular partner is defined in your system?

      As per my understanding if you are recieving goods from vendor to your company then it should be inbound delivery?? I understand you defined Hub as a vendor wich supply goods to your company code....

      What happens when you are creating this delivery manually do you find same error in this case?

      Regards

  • Posted on Sep 01, 2013 at 04:39 AM

    HI Madhav,

    Have You done this scenario. If still facing issues refer this document..

    http://scn.sap.com/docs/DOC-45777

    Regards

    Satish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.