on 08-26-2013 3:47 PM
Hi,
Am working in ECC 6.0 IDES system, comfiguring ABAP proxy towards a PI system.
In SLDAPICUST tcode I had made the entries pointing towards the PI's SLD.
For testing the connection, am not able to find the TEST button at the top and also in the menus as well.
please advise on this..
Regards,
Dino
Hi all,
Thanks for your reply.
The issue has been fixed now. Now the TEST button got enabled in SLDAPICUST Transaction.
Earlier the SAP system was in NW 700 SP13. "We upgraded the SP level to SP22".
Hence, now the functionality got enabled. And TEST button in available.
Best Regards,
Dino
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dino,
If you want to check the connection, you can do with SLDCHECK also
Regards
Hari.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dino,
Test button is only available since 7.00 basis version. Check this Note 1432661 - Connection test for transaction SLDAPICUST
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Dino,
The Test button functionality was only introduced in the later NetWeaver releases (I think it is only available from NW 7.1). I am not sure what exact release your ECC 6.0 system is, but most likely it is older than NW 7.1 and hence the functionality does not exist in that release. Most likely that is why you can't find the Test button.
Regards
Mark
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
83 | |
10 | |
10 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.