Hi,

I configured the track sync in nwdi cms between N and N+1 tracks.

So that whenever the developer releases the activity for N track, that activity should be available

in Consolidation tab of N+1 track.

But this method is not working in NW 7.31.

Please suggest.

Thanks,

RY

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 22, 2013 at 05:41 PM

    Hi Ravi,

    Please have a look through below link which might be helpful.

    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/b08abb67-0e34-2d10-78b8-e7246ad93fb2?QuickLink=index&overridelayout=true

    Thanks & Regards

    Amit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks Amit. I already have this document. The NWDI system was all setup and running fine.

      We are building track sync for already existing tracks to sync the code between N(prod landscape) systems and N+1 systems.

      Appreciate your response.

      Thanks,

      RY