Dears,

Could you please tell me the way to update Current period of Cost estimate in material master?

Thanks & Best Regards,

Quang

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Adnan Ahmed Jan 12, 2017 at 05:25 AM
0

Hi ,

1. Execute cost estimate of the material with no error ( CK11n) and save.

2. Mark the price for the material using CK24 ( This will update future price tab of the material master)

3. Release the price for the material with the same t-code CK24 ( this will update the current price tab)

Regards

Adnan