Dears,

Could you please tell me the way to update Current period of Cost estimate in material master?

Thanks & Best Regards,

Quang

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 12, 2017 at 05:25 AM

    Hi ,

    1. Execute cost estimate of the material with no error ( CK11n) and save.

    2. Mark the price for the material using CK24 ( This will update future price tab of the material master)

    3. Release the price for the material with the same t-code CK24 ( this will update the current price tab)

    Regards

    Adnan