BOM Explosion while Manual Production Order

former_member229388
Participant
0 Kudos

Hello Experts,

I am very new to SAP PP.

I have a BOM for Part "A", which has components "B", "C" and "D".

And Component "D" also has BOM which has components "E" and "F"

So now when I create Production Order manually for Part A, is there any way I can explode BOM for D as well?

Or in the case of manual production order creation, I have to create Orders for A and D independently?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you define the special procurement "phantom assembly" for material D, the BOM will be exploded in the production order of material A.

Regards,
Caetano

Answers (2)

Answers (2)

0 Kudos

Hey guys,

can I just check that if you create a Manual Process Order (using PP-PI) even if you have a BOM within the final part the MRP run will only explode to one level and you need to run MRP for your dependent BOM also ?

The Phantom Assembly setting did not seem to have any affect. I don't want to set this part up as a Phantom as it is BOM in itself.

cheers David

solomon_macwan
Active Contributor
0 Kudos

Hi Dhananjay,

if you create manual production order than it will explode bom for A material only. When you create a Production order for material D, than only it will explode the bom for D.

if you want to understand how bom selection happens, please follow below link

https://blogs.sap.com/2015/06/03/bom-selection-in-mrp/

Regards,

Solomon