Hi,

My client has a requirement for creating purchase requisitions based on different planning horizons for raw materials.

My forecast horizon is 1 year.

e.g

Raw material -1 = only 1 month Purchase reqs needs to be created, the rest 11 months should be planned orders.

Raw Materi - 2 = 3 months PR needs to be created and the rest 9 months shoudl be planned orders.

Raw Matwerial - 3 6 months PR needs ot be created and the rest 6 months shoudl be planned orders.

Can i map this in SNP ??