Hi,

I have production orders (PP01) with equipment PRT assigned to operations.

I have maintained my PRT master data and when I confirm my operation my measuring point gets updated correctly.

It also schedules dates on the operation correctly.

But it just doesn't update the actual dates. I wanted to know how the update of actual dates can be done.

I also figure that when I confirm the "Start date for setup" time event for my operation through CO19 tcode, the equipment PRT should change its status, so that if make an availabilty check for another PP order, the availabilty check should fail as it is being used on the first order, but I am not able to figure out how its done.

Would be very glad if someone could help me with these two topics.

Many thaks,

Carlos.