Hi Guru's,
I don't understand why for some production orders in our system the consumption targets are calculated based on the planned production quantities instead of the actual quantity? For example , the target quantity for the material X should be 1,935.78 based on the production of 18,480 eaches actual qty ( planned qty is 16,800 eaches) and the scrap rate of 4.75%? Instead I am seeing
Total target qty of 1,759.80
Total actual qty 1875.35
Target/actual var 115.55
Total Target costs 990.86
Total act. cost 1,05.84
Target / actual var. 64.98
Any help will be much appreciated. thank you !
Best Regards,
Yasmeen