Allocation Procedure Customizing

Hello,

I am customizing a multiple allocation procedure, that has 3 allocation procedures checks. And I want to avoid the following situation:

A sales order require 100 crt for product xxxzzz

Result: 100 crt confirmed

Procedure 1: no confirmation

Procedure 2: partial confirmation (50 crt )

Procedure 3: partial confirmarion (50 crt )

I want the following result:

Expected result: 50 crt confirmed

Procedure 1 no confirmation

Procedure 2: partial confirmation (50 crt )

Procedure 3: no check or no confirmation

What I am expecting is to have an "OR" condition (procedure 1 "or" procedure 2 "or" procedure 3).

Is it possible?

Thank you.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Aug 12, 2013 at 07:00 PM


    Hello Al,

    As per my understanding, Product Allocation procedure sequence doesn't allow OR condition the way you explained.

    Although Business requirement is not clear. So I will suggest to reevaluate your business requirement. Because the scenario which you explained above may be caused by technical settings/configurations exist in your current system.

    But if any of the Business requirement does not fit into your current solution. You may like to reconfigure Product Allocation Group with desired Characteristics and then setting up Allocation procedure for the same.

    Thank you

    Satish Waghmare

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 11, 2013 at 07:41 PM

    Hi Al,

    Results of allocation procedure sequence seems to be correct to me.

    I believe what you are trying to achieve will be possible with a sequence of allocation groups not with sequence of allocation procedures.

    With sequence of allocation groups as well you can only do a sequential evaluation i.e. result of preceding step if passed to subsequent step and so on.....

    below is the graphical flow of this calculation and few tips what all can be done here.

    Please let me know for any further query.

    Rgds

    Sourabh


    pastedImage_1.png (21.2 kB)
    pastedImage_0.png (48.4 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Al ,

      "Expected result: 50 crt confirmed

      Procedure 1 no confirmation

      Procedure 2: partial confirmation (50 crt )

      Procedure 3: no check or no confirmation

      What I am expecting is to have an "OR" condition (procedure 1 "or" procedure 2 "or" procedure 3)."

      If you are going for Product Allocation Procedures and then maintaining a sequence of them then you will get above result only . How it works is "All the conformed qty from different procedures will be added to arrive at a final confirmed qty" .

      First the requested quantity will be checked against the first Procedure and if there is a partial confirmation or no confirmation it will move to the next Procedure in the sequence . This goes on until it finds either the end or req qty gets confirmed .

      May be if you can be more specific with the desired system behavior then I will able to give more details on the same .

      Hope this is helpful . 😊

      Best Regards ,

      Love Singh

  • avatar image
    Former Member
    Aug 12, 2013 at 12:43 PM

    Thank you for your answers.

    I understand the behavior when I use Product Allocation Sequence. But maybe I shouldn´t use an Allocation Sequence becouse I look to use just one Allocation Group.

    What I am trying to have as a result is to use Allocation Group 1 "or" Allocation Group 2 (let´s simplify the case with 2 allocation groups).

    If there´s no quota available in Allocation Group 1, try to consume quota with Allocation Group 2.

    Now I´ve configured one Allocation Procedure with two Allocation Groups in it. But If the Allocation Group 1 doesn´t confirm quota, it doesn´t proceed to check Allocation Group 2. I get this message: "No requirement was transferred for the product allocation step"

    Do I have to configure something else ? Is it possible?

    Thank you!

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      The requirement is to upload the quotes like this:

      SKUChar 1Char 2Char 3Quoteyyyy*********0yyyyYO25******0yyyyYO252233***50yyyyYO252233Y850yyyyYO25***Y850

      As you can see, the last row, will not read properly, and the system will "jump" to check the second row.

      So, a possible solution would be to create a second allocation group for the system could read the last row as below:

      SKUChar 1Char 3Char 2QuoteyyyyYO25Y8***50

      Allocation group 1: SKE_CHAR1_CHAR2_CHAR3

      Allocation group 2: SKE_CHAR1_CHAR3_CHAR2

      I know that the requirement it´s kind tricky and it´s not the best way to use the quotes, but the business insist to use these cvc´s.

      Thanks!

  • avatar image
    Former Member
    Sep 25, 2013 at 06:30 PM

    Hello,

    We have concluded that the requirement must be make by custom development.

    Thank you for your support!

    Add comment
    10|10000 characters needed characters exceeded