Former Member
Jul 31, 2013 at 11:55 AM

order scheduling

24 Views

Dear experts,

i had 2 operations for my finished product. my requirement is that if first operation starts today ,second operation should be started tomorrow. i had maintained quee time for 2nd operation . but system is calculating quee time from the end of first operation . but my requirement is system should calculate quee time from start time of first operation

i had order of 2000 ea, base quantity is 100 ea ,maintained quee time as 24 hrs in 2nd operation . system is showing like this

31.07.2013 operation 0010 start time 8.00 am , end time 5.00am on 01.08.2013

adding 24 hrs quee time from 01.08.2013 5.00am

02.08.2013 operation 0020 start time 5.00am , end time 1.00am on 03.08.2013

but my requirement is

31.07.2013 operation 0010 start time 8.00 am , end time 5.00am on 01.08.2013

need to add 24 hrs quee time from 31.07.2013 8.00am

01.08.2013 operation 0020 start time 8.00am , end time 1.00am on 02.08.2013

Thanks,

ramayya