Dear experts,
i had 2 operations for my finished product. my requirement is that if first operation starts today ,second operation should be started tomorrow. i had maintained quee time for 2nd operation . but system is calculating quee time from the end of first operation . but my requirement is system should calculate quee time from start time of first operation
i had order of 2000 ea, base quantity is 100 ea ,maintained quee time as 24 hrs in 2nd operation . system is showing like this
31.07.2013 operation 0010 start time 8.00 am , end time 5.00am on 01.08.2013
adding 24 hrs quee time from 01.08.2013 5.00am
02.08.2013 operation 0020 start time 5.00am , end time 1.00am on 03.08.2013
but my requirement is
31.07.2013 operation 0010 start time 8.00 am , end time 5.00am on 01.08.2013
need to add 24 hrs quee time from 31.07.2013 8.00am
01.08.2013 operation 0020 start time 8.00am , end time 1.00am on 02.08.2013
Thanks,