Hello Gurus,
I would like to know SAP takes which settigns as priority, whether system takes Material master setting as priority or MRP group configuration?
Hello
The priority is to the settings defined on the material master. MRP group settings are only considered if they are empty on the material master.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
The following information is provided on question 2 of FAQ note 772856:
2. Question:
Which consumption parameters (Consumption mode/consumption period)
are taken into account?
Answer:
The parameters maintained in the material master (material
requirements planning view 3) have the highest priority. If you do
not specify a consumption mode, the system uses the consumption
parameters from the MRP group that is assigned to the material. If a
consumption mode is not specified there, the consumption mode is set
to '1' by default (backward consumption only) with a (backward)
consumption period of 999 days. This means that the consumption
cannot be deactivated because the consumption parameters have not
been maintained. The consumption periods are calculated in workdays.
BR
Caetano
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.