Consumption Mode, MRP 3 View setting or MRP group configuration priority

Former Member
0 Kudos

Hello Gurus,

I would like to know SAP takes which settigns as priority, whether system takes Material master setting as priority or MRP group configuration?

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The priority is to the settings defined on the material master. MRP group settings are only considered if they are empty on the material master.

BR


Caetano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

The following information is provided on question 2 of FAQ note 772856:

2.  Question:

    Which consumption parameters (Consumption mode/consumption period)

    are taken into account?

 

    Answer:

    The parameters maintained in the material master (material

    requirements planning view 3) have the highest priority. If you do

    not specify a consumption mode, the system uses the consumption

    parameters from the MRP group that is assigned to the material. If a

    consumption mode is not specified there, the consumption mode is set

    to '1' by default (backward consumption only) with a (backward)

    consumption period of 999 days. This means that the consumption

    cannot be deactivated because the consumption parameters have not

    been maintained. The consumption periods are calculated in workdays.

BR

Caetano