Dear Expert,

I have several operation in a routing.

10 - Drill section A

20 - Drill section B

30 - Drill section C

---

40 - Coating

50 - Finishing

Operation 10, 20, and 30 can be done with a random sequence like (10, 20, 30) or (20, 10, 30) or (30, 10, 20).

And after that operation, operation 40 and 50 must be done by sequentially.

But user required to check operation like below in Define Confirmation Parameters

How can SAP handle it?


NB:

I try parallel sequence for op 20 and 30 but op 40 can be confirmed if any confirmation for op. 10 while no confirmation for op 20 and 30.

Regards,

Akbar Arsyad