Hi,

We are having an issue with the scheduling of a production order.

We are going for backward scheduling and maintaining the end date in the production order as 4th September 2013.

But after clicking on the rescheduling button, it's picking the end date as 28th August 2013.

Please guide us.

Thanks and Regards,

Kaushik