WCM- Permit Extension for applications and Op WCD

Hi SAP WCM Experts

I'm doing WCM(Work Clearance Management) enhanced model implementation. I've configured permits like Cold Work, Hot Work permits etc as applications.

I want to ask this "How to configure extension of application in this "?

E.g If permit validity is 1 day and it needs to extended for more 3 hours becuase work has not finished as of now. Is there any possiblity to do this with standard settings in WCM.

I heard there is some standard functionality available from EHP5 to do this activity.

Please advise.

Regards

Rahul

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 23, 2014 at 06:25 AM

    Dear Sandeep,

    the function-based extension was developed for release SAP 6.0 EhP 5. This function was required for the WPM configuration but can also be used for other configurations. But this function is only available for the Applications.

    See the following IMG Activity: Maintain Usage of Applications. In this IMG activity, you define the usage for your applications. Note the following special features:

    • You can shift the start of an application's validity.
    • You define the duration of the validity (in hours).
    • You can define a function-based extension of the validity (of a certain amount of hours).

    Regards Uwe

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 06, 2013 at 12:56 PM

    Dear Sandeep,

    It is not possible in standard configuration. To achieve this...

    If the permit is in prepared you need to reset prepared then system will allow you to change the valid from and to date. If system won't allow you to do so please check this path SPRO-PM-WCM-Maintain Application profile-filed selection remove check box fld.sel.Appl. then system will allow to make changes.