cancel
Showing results for 
Search instead for 
Did you mean: 

Excess SNP Planned order creation

former_member691361
Participant
0 Kudos

Hi,

Extra SNP planned orders are created eventhough stock on hand is available while executing the SNP heuristic in batch job and it is getting corrected if running the same product manually in planning board.It is happening only for few products.

What could be the possibilities for the same and how to rectify it?

Thanks,

Prasanth

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187488
Active Contributor
0 Kudos

Hello, Most of similar problems are due to incorrect low level codes. Please run low level codes determination in transaction /sapapo/snpllc before running heuristic in batch. Check the low level codes for corresponding products/locations in transaction /sapapo/rrp_netch if you want.