Hi,

I have maintained SNP horizon days as 50 and not maintained anything in PPDS horizon.

But when i am running SNP heuristic, SNP planned orders are created inside the SNP horizon and later the SNP orders are not deleted while running PPDS heuristic.Means the SNP orders are still available in SNP horizon.

Could you please guide me what could be the reason.Do it has some impact with the SNP horizon maintained in receipt product and requirement product?

Please let know the possibilities for this error?

Thanks,

Prash

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Jul 25, 2013 at 12:37 AM

    Hello Prash, The heuristic result should not be correct, means no order should be created in the snp horizon. I think there're many notes regarding SNP scheduling ... you can search the notes with "too early" or "inside, horizon" something like that ...

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 31, 2013 at 10:18 AM

    Hii Prasanth,

    You can check for following S notes,

    1542205

    1555644

    1568244

    1572673

    1601536

    1649238

    Regards

    Debashis