on 07-23-2013 12:19 PM
Hi Everyone,
There is a program which runs in SAP triggered by Cronacle. Program generates two spools in SAP, one is for a team to send the PDF file and the other is for the report spool. Spool is not getting returned to Cronacle. Spool flag is set to yes in the parameters. Is there any configuration which can be made in Cronacle or SAP so that the report spool can be returned to Cronacle. For all other jobs spool is visible in Cronacle.
Thanks in advance for the help.
Regards,
Ramana
Hi HP/Jane/Shailesh,
In the job definition, the format is set to 'Generic' in DEV, QA and PROD. The spool is returned to CPS in dev and qa but in prod, ONLY for this job the spool is not returned to CPS from SAP. For other jobs in PROD, the spool is getting returned. I have tested the job by directly duplicating the job from QA as well as directly duplicating a job in PROD which shows spool.Still there is no spool visibility.
CPS Version 7.0.4.8 SP8 in all the environments. We have checked SM21, there were no errors for the instances it ran till now.
Also I have mentioned the logs above in the chain.
Thank you for all your help in advance.
Thanks,
Ramana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Ramana
in this case, pls upload job log for a look. this is checking if spool is generated on SAP successfully or not.
assuming that PRD has everything same wtih QA, DEV, including transport files, if spool is generated on SAP side, perhaps you need to set RFC agent to DEBUG level to capture more info.
furthermore, advise you to open a SAP ticket, this might request more files or tracing for troubleshooting.
regards Jane
HI,
Please share job log
regards
shailesh kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi, Romana
what's your CPS version and patch level? there's possibly something happened on SAP side. pls check SM21, especially RZ15 on that day for this job.
what's job definition used for running this program on CPS side? does it always fai to generate spools files?
does Quality system have same CPS version and patch level with this one?
Jane
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It works fine in Quality. The issue is only in Production. It displays the below log in Production.
ZBO_SAMPLE_INVOICES2/06000507: opened
ZBO_SAMPLE_INVOICES2/06000507: step 1 execution of ZBO_INVOICE_DASHBOARD
ZBO_SAMPLE_INVOICES2/06000507: closed
ZBO_SAMPLE_INVOICES2/06000507requested to run as soon as possible
ZBO_SAMPLE_INVOICES2/06000507: Step 1 has no spoollist id
------------------------------------------------------------------------------
ZBO_SAMPLE_INVOICES2/06000507: PROTOCOL LOG
2013.07.24 06:00:05 : S-00-516: Job started
2013.07.24 06:00:05 : S-00-550: Step 001 started (program ZBO_INVOICE_DASHBOARD, variant , user ID REDWOOD)
2013.07.24 06:39:14 : S-00-517: Job finished
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramana,
Could you please inspect the job in SAPGui and tell me what the format of the spool files is that is failing?
Could you also look at the job definition in CPS and tell me what the format is ? You should set this to PDF if you want the PDF. If you use SAP_AbapRun* job definition, you can duplicate it and change the format.
Regards,
HP
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |