Forward scheduling with standard lots PP heuristics (SAP_PP_002)

Hi,

I am trying to change planning mode in strategy tab of standard lots PP heuristics (SAP_PP_002). It is greyed out for Forward & Forward+reverse.  We would like to use Forward scheduling. Have any of you come across this issue?

thanks in advance,

subramanya

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jul 24, 2013 at 10:31 PM

    Hi Subramanya,

    Make a copy of the heuristic and you'll be able to change it to your requirements.

    SAP standard supplied objects should never be changed.

    Best Regards,

    Mike