Hi All,

I have below scenario how to do the billing in schedule line items with diffrent dates.

SO 31XXXXXXX

item quantity

1 25

in schedule line item

Delivery date order quantity

16.01.2013 5

20.06.2013 10

30.9.2013 8

01.12.2013 2

First I need to do the billing for 16.01.2013 and 20.06.2013 date remaining I will do it when ever it is needed.

Please advise.

Thanks,

Preddy