I want to create a multiple counter plan for vehicles as I need to do preventive maintenance on every 10000KMS or 3 Months whichever comes early. I am able to simulate this scenario in SAP using multiple counter plan, but still need your advice on below points.
Regards
Atul Rajmane
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Start counter Reading field will appear in maintenance plan creation mode and before scheduling. Please make sure that a measuring counter is attached to the maintenance plan.
Regards,
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pawan,
Thanks for the response.
It solves most of my queries.
Could you let me know where this fieldcUse "Start counter reading" in maintenance plan is defined as I am unable to locate same. A screen shot would be helpful for me.
Regards
Atul Rajmane
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atul,
The scenario can be done by Multiple Counter Plan.
1. Counter over flow reading: The last reading your vehicle can measure (Odometer Reading). The significance is when the vehicle reaches the max reading either it will be replaced or reset to zero. In your case, imagine a meas document was created at 99,99,995. When next meas document is created with value 5, the total unit your vehicle moved is 9.
2. No. Annual Estimate is the approx. km run by vehicles annually. It is related to your query 5, imagine a vehicle runs approx 10,000 km per year and maintenance is done once in 5000 km. Now vehicle is abandoned or stopped using after using 2000 km within 3 months, if counters are not regularly updated with 2000 even if vehicle not used, system thinks user has forgotten to enter the reading and it will trigger call object.
The logic involved is
https://blogs.sap.com/2014/07/18/next-plan-date-calculation-logic-for-multiple-counter-plan/
3. Use "Start counter reading" in maintenance plan.
4. Yes
5. Clubbed with query 2.
Regards,
Pavan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.