if we change the route in delivery, can we have scheduling dates in DELIVERY Document to redetermine

Former Member
0 Kudos

Friends,

I was exploring options on one of the Buz scenario to re-determine the scheduling dates in DELIVERY Document, if I change the route in teh delivery.

So if we change the route in delivery, can we have scheduling dates in DELIVERY Document to redetermine, based on the new route.

Greatly appreciate your advise.

Vijay.

Accepted Solutions (1)

Accepted Solutions (1)

former_member223981
Active Contributor
0 Kudos

In transaction OVLK, you can set if "Rescheduling" is executed in the delivery.

So for example, if you change the route in VL02N and want a new scheduling, you can set "Rescheduling" (in OVLK) to "Y" or "A". This will ensure a new scheduling gets triggered when you change the route

Former Member
0 Kudos

Thanks Noel, please bear my delay, as i got the answer on further research.

Regards

Vijay

Answers (1)

Answers (1)

former_member205178
Contributor
0 Kudos

Hi,

Route while it does impact the dates in the delivery, it has to do with the Transportation Times. You might want to invoke Availability Check during the Delivery to play with the Delivery Schedules.

Thanks.