on 07-16-2013 1:18 PM
Hi Expert,
We are implementing new process for issuing raw material against process order.now we need to create TR after liquid order creation.
Current condition in system: After confirmation (COR6N) system creates TR.
Reuirement: Before confirmation we need to create the TR in the system.
Please give the details or solution.
Regards,
Ram Rathode
Hi Ram,
While creation of liquid/process order only reservations will create, we can not create TR against reservation. TR will be create once the goods movement happen at IM level as per standard.
Try with create Z-movement with manual TR creation option, create TR in LB01 with reference to your liquid/process order. But need to take care goods movement has to happen at IM level. Otherwise stock diff will come.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per my understand on your issue , You need to create TR before confirmation ,
create Z Table like transparent table to update one number Tr automatically and put restrict it should not be equally to existing TR's .And after confirmation the Process update directly TR from Z table what ever created reference . Any we have option in configuration to put particularly field value as a TR.
Hope it is helpful to you
If my understanding wrong please detail on issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This requires WM-PP interface setup. Please check below link.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thank you for your valuable reply. now we are getting below error while doing wm staging in process order "Stor. location in PUB (RMWH) is not the same as prod.stor.location (WELM)"
Note:( We have two prod.locations i.e RMWH and WELM and we have created two production supply area i.e 251 and PPL so assinged to PSA to prod. locations.)
OR
Is it possible for two PSA and two production location for same material because of in material master we can maintain only one PSA or prod. location?
Regard,
Ram
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.