on 07-15-2013 6:35 PM
Hello Experts,
I am not able to view cost element in cost analysis screen for rework work center in the production order. Work center is assigned to cost centre and activity types maintained.
Your inputs are highly appreciate.
Thank You
Regards,
Radhika
Dear,
In the material master have you maintained 'Material Origin' in the Costing 1 tab?
Are you using routing or reference operation set in rework order?
Could you please share the screen shot of CO03, Go To --Cost Analysis--Itemization
If you settle the rework costs of the separate production order under a settlement cost element to the original production order, you can identify the rework costs through the settlement cost element.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Radhika,
check the layout of cost analysis and select cost element from the list in production order.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.