Hi All,

In our project we are using RA method( cost based method -07) when i have the planning cost  (material and labour hrs) in the project. Here , issue what i am facing is till there is only showing planned material cost of the project , in KKA2 i can see the planned cost, but I am not able to see planned hours in my result analaysis kka2 if i refer any PS reports i can see the plan cost there. but i can see plan revenue as well .

I am confused with this kind of system behaviour. Kindly suggest me what shall i do to overcome this. In our scenario in valuation method i am ausing over all plan  : E  and over run : A

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member201529
Active Contributor
0 Kudos

Dear Kishore,

As per my knowledge we would not get any planned hours in KKA2 transaction.

Regards,

Karna J

sibal_sahoo
Member
0 Kudos

Go to SPRO and check setting OKGB and OKGA .

former_member183750
Active Contributor
0 Kudos

Hello

Please note the description from the Overview for this SCN Space:

Official SAP Help Portal Community. Find comments on SAP product documentation (such as SAP Application Help, also known as SAP Library), and read best practices shared by the community.

Based do the above, I believe you posted your query into the incorrect SCN Space. Please use the Forum Finder for the New SCN document to find your product and post into that SCN Space.

Also  seeing as you did not provide any product information, I would also highly recommend reading the SCN Rules of Engagement.

With best regards,