Skip to Content
0
Former Member
Jul 12, 2013 at 06:52 AM

Problem while running KKA2 (result analysis) RA method 07(POC)

219 Views

Hi All,

In our project we are using RA method( cost based method -07) when i have the planning cost (material and labour hrs) in the project. Here , issue what i am facing is till there is only showing planned material cost of the project , in KKA2 i can see the planned cost, but I am not able to see planned hours in my result analaysis kka2 if i refer any PS reports i can see the plan cost there. but i can see plan revenue as well .

I am confused with this kind of system behaviour. Kindly suggest me what shall i do to overcome this. In our scenario in valuation method i am ausing over all plan : E and over run : A

Thanks