on 06-27-2013 4:45 PM
Hello,
is it possible with CPS to grant a user access rights, so he can only restart a failed process chain?
In the full version it is possible, but it looks like in CPS there are limits.
I am looking for the role/privileges documentation ...
Thanks for your help.
Best regards
Carlos Behlau
Have you tested the different privileges available for Job Definitions?
There is not a separate object type for BW Process Chains.
I would expect you to be able to lock them down to scheduling them (including restart) - this privilege would prevent people from creating/editing/deleting the Job Definitions for the Process Chains.