Special Procurement Key doesn’t create T-lane in APO

Hi All,

We are using special procurement key in E.C.C materiel master. As per standard process special procurement key should create T-lane in APO.

But their is some customization done to stop special procurement key to update T-lane in APO.

No CIF enhancement exists in the system to block special procurement key.

Please suggest if their is any other way to stop special procurement key (code change or some enhancement spot etc) to stop creating T-Lanes.

Thanks

Regards,

Amlan C

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 26, 2013 at 11:58 AM

    Amlan,

    Do you have an integration model created and activated that includes the material and Plant?

    What is the SPK you are using?

    If the purpose of the SPK is to source the product from another location, does that location exist in APO?  Does the product exist in the source location in APO?

    Have you tried running RIMODINI in ECC against the Material Integration model? 

    Are there any messages in the logs?  Are there any blockages in the queues (SMQ1 and/or SMQ2)?

    Best Regards,

    DB49