Production planning run

hi ,Its rather intrigue-ing  abt this error 

i have set a standard hiuristic pp_001 and function as change order manually ..the line of reasoning behind this setting in case hiuristics doesnt deliver an accurate plan....then i will have to do additional planning manually ..but to my dismay i find a error "" hiuristic change order manually cannot be used in the production planning run""   ...i agree there is GAP between my reasoning and system reasoning..i seek your wisdom in bridging the gap

ppr.jpg (42.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jun 28, 2013 at 08:59 AM

    Dear,

    If you change an order, the system executes the standard heuristic SAP_PP_001 for changing orders (/SAPAPO/HEU_ORDER_CHANGE)which is entered in Customizing forProduction Planning and Detailed Scheduling(PP/DS) under Maintain Global Parameters and Defaults, in the standard system


    You can not use this heuristic in /SAPAPO/CDPSB0 - Production Planning Run .

    Please refer SAP help for more details,

    http://help.sap.com/saphelp_scm50/helpdata/en/2e/c0703713bf277ee10000009b38f8cf/content.htm

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      thanks rupesh  ..... i will sit and do a detailed study  from your clue...will get back to you