on 06-24-2013 7:41 AM
hi ,Its rather intrigue-ing abt this error
i have set a standard hiuristic pp_001 and function as change order manually ..the line of reasoning behind this setting in case hiuristics doesnt deliver an accurate plan....then i will have to do additional planning manually ..but to my dismay i find a error "" hiuristic change order manually cannot be used in the production planning run"" ...i agree there is GAP between my reasoning and system reasoning..i seek your wisdom in bridging the gap
Dear,
If you change an order, the system executes the standard heuristic SAP_PP_001 for changing orders (/SAPAPO/HEU_ORDER_CHANGE)which is entered in Customizing forProduction Planning and Detailed Scheduling(PP/DS) under Maintain Global Parameters and Defaults, in the standard system
You can not use this heuristic in /SAPAPO/CDPSB0 - Production Planning Run .
Please refer SAP help for more details,
http://help.sap.com/saphelp_scm50/helpdata/en/2e/c0703713bf277ee10000009b38f8cf/content.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.