Dear All,

In Capacity requirement planning does system considers material availability functionality in any of it's transactional flow?

I want to clarify to my client that material availability check is any how related with capacity reqmt plng or not?

Thanks,

Naresh

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

If you are taking for MRP point of view then it is not possible. Else in production order you can do the material availability check and capacity check too according to the configuration of OPJK.

Use profile SAPSFCG013  SFC:Capacity availability check and remove no check for your order type and plant combination.

Also refer the below link,

http://scn.sap.com/thread/3178493


Regards,

R.Brahmankar

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks a lot. I am closing the thread.

Naresh

Former Member
0 Kudos

Dear ,

         Capacity check by default deals with machine/labor  Availability (not with Materials). So, you can very well say that it is 'No way' Related (directly)