on 06-20-2013 10:07 AM
Hi Expert,
We are facing one issue in GATP. When we are changing the delivery date to today’s or tomorrow’s in STO, the system is assigning the delivery date in past by user ALEREMOTEAPO.
eg. when we change the delivery date of STO from 11.06.2013 to 13.06.2012 in R/3, immediately APO changes it to 29.04.2013.Planned delivery time is 45 days.
I can not understand the behavior of APO system . Please let me know what I need to check to resolve the issue.
Regards
Sachin
Hi Sachin,
The question is which event is changing the delivery date due to APO. Please check the EDQA
monitor in transaction /SAPAPO/EDQA if you find a EDQA BOP which is doing this.
Please make sure that the scheduling is activated for the STO. Recheck your customizing in ECC
SAP Customizing Implementation Guide
Materials Management
Purchasing
Purchase Order
Set up Stock Transport Order
-> Assign Delivery Type and Checking Rule
Recheck your userexits in scheduling:
FM EXIT_/SAPAPO/SAPLVCRM_001 & EXIT_/SAPAPO/SAPLVCRM_002
Hope this helps.
best regards,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.